Planning Application

Case number W/14/00237/CU

Proposed conversion/change of use of existing barn to provide 3No.residential units. One quarter of barn retained for use by Hyde Farm. Existing access road at site entrance widened to provide two way movements.

Location: Hyde Farm, Worcester Road, Pinvin, Pershore, WR10 2DX

Other planning applications at this location View location on map

Application Type: Change of use

Parish: Pinvin

Ward: Drakes Broughton

Application Received: 5 February 2014

Statutory Start Date: 4 March 2014

Consultation Period From: 7 March 2014

Consultation Period End: 4 April 2014

Decision Date: 15 April 2014

Case Officer: Lynn Bailey

Status: Decided

Decision: Approved - Change of Use

This decision is subject to the following conditions:

  1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

    Reason - In accordance with the requirements of Section 91 (1) of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

  2. No part of the development shall be commenced until full details of soft landscaping works have been submitted to and approved in writing by the Local Planning Authority. The details submitted must include:

    i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread. ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas. iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants. iv) a written specification outlining cultivation and other operations associated with plant and grass establishment. v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting.

    All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner.

    Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless otherwise agreed in writing by the Local Planning Authority.

    Reason - To protect and enhance the visual amenities of the area and to ensure the satisfactory development of the site - in accordance with Policy GD2, Policy ENV1 and Policy SUR2 of the Wychavon District Local Plan (June 2006).

  3. Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter. Reason - To ensure that an appropriate sustainable drainage system is provided to serve the development and to reduce the consumption of water. This is in accordance with the SPD on Water Management.

  4. The development hereby permitted shall not be brought into use until the access, turning area and parking facilities shown on the approved plan have been properly consolidated, surfaced, drained and otherwise constructed in accordance with details to be submitted to and approved in writing by the Local Planning Authority and these areas shall thereafter be retained and kept available for those uses at all times.

    Reason - In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.

  5. The materials to be used in the construction of the external surfaces of the replacement corrugated sheeting hereby permitted shall match those used in the existing building.

    Reason - To ensure that the proposed works are executed in materials, which harmonise satisfactorily with the existing building.

  6. The development hereby permitted shall be carried out in accordance with the following approved plans:

    1304/03, 1304/04, 1304/05, 1304/06, 1304/02, 1304/01

    Reason - To define the permission.

  7. Unless otherwise agreed by the Local Planning Authority development, other than that required to be carried out as part of an approved scheme of remediation, must not commence until Parts 1 to 6 have been complied with:

    Part 1. A preliminary risk assessment must be carried out. This study shall take the form of a Phase I desk study and site walkover and shall include the identification of previous site uses, potential contaminants that might reasonably be expected given those uses and any other relevant information. The preliminary risk assessment report shall contain a diagrammatical representation (conceptual model) based on the information above and shall include all potential contaminants, sources and receptors to determine whether a site investigation is required and this should be detailed in a report supplied to the Local Planning Authority. The risk assessment must be approved in writing before any development takes place.

    Part 2. Where an unacceptable risk is identified a scheme for detailed site investigation must be submitted to and approved in writing by the Local Planning Authority prior to being undertaken. The scheme must be designed to assess the nature and extent of any contamination and must be led by the findings of the preliminary risk assessment. The investigation and risk assessment scheme must be compiled by competent persons and must be designed in accordance with DEFRA and the Environment Agency's "Model Procedures for the Management of Contaminated Land, CLR11"

    Part 3. Detailed site investigation and risk assessment must be undertaken and a written report of the findings produced. This report must be approved by the Local Planning Authority prior to any development taking place. The investigation and risk assessment must be undertaken by competent persons and must be conducted in accordance with DEFRA and the Environment Agency's "Model Procedures for the Management of Contaminated Land, CLR11".

    Part 4. Where identified as necessary a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.

    Part 5. The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development, other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority.

    Part 6. Following the completion of the measures identified in the approved remediation scheme a validation report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings.

    Part 7. In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where necessary a remediation scheme must be prepared, these will be subject to the approval of the Local Planning Authority. Following the completion of any measures identified in the approved remediation scheme a validation report must be prepared, which is subject to the approval in writing of the Local Planning Authority prior to the occupation of any buildings.

    Reason:

    To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.

View application at Wychavon website View planning documents

Top of page

Applicant

Mr & Mrs E Jaques
Hyde Farm
Worcester Road
Pinvin
Pershore, Worcs

Agent

Mr Nicholls
Guy G Nicholls
95 Market Street
Kingswinford
West Midlands (Met County)

Other planning applications at this address

W/14/02800/CU
Date: 25 February 2015
Change of use: Refused - Change of Use
Use of land for the stationing of up to 15 caravans for recreational and leisure purposes with landscaping, hard standings, drainage and access ancillary to that use.
More details...
W/12/01748/CU
Date: 13 September 2012
Change of use: Approved - Change of Use
Proposed conversion/change of use of existing barn to provide 3no. self contained offices. One quarter of barn being retained for the use of Hyde Farm.
More details...

Top of page

Location Map

Note: The map marker shows the approximate centre of the application postcode, if available, or the nearest geocoded location from the address. The actual location may be slightly different.

Top of page